“Mismatch in Reforms is Causing Avoidable Adverse impact on Economy”

Ram V. Shahi, Former Power Secretary, Government of India, shares The Dynamics between Power and Coal

Ram V. Shahi, post his tenure as Power Secretary, has been associated with various organisations as head of their energy advisory boards. In an exclusive interview with B&E, he shares the interdependence of the coal and power sectors

B&E: How will the cess of Rs.50 per tonne levied on coal affect power tariffs in the short to medium term?
RVS:
The cess of Rs.50 per tonne on coal will have an effect on the cost of power generated in coal based power stations in the range of 3 paise to 4 paise per KWhr. Its effect at the level of consumer tariff, however, will be of the order of 5 to 6 paise per KWhr in view of transmission and distribution loses. This cess, which will lead to revenue, on a national basis, of the order of Rs.30 billion per year, will go towards encouraging Green Energy. In this very budget, Service Tax on Transmission has been abolished. Therefore, positive impact of abolition of Service Tax would be about 5 paise per unit if we consider inter-regional transmission of power. Thus, additional burden on account of coal cess is more or less offset by the concession in Service Tax.

B&E: How will the move to allow open auctions for coal mining blocks affect fuel availability for power plants and what will be the effects on consumers?
RVS:
The proposed initiative for coal mine development by allotting coal blocks on the basis of competitive bidding is a positive one. However, the criterion for evaluating bids should be the cost of producing coal rather than any premium that the mine developer may be asked to offer to the Government. Development of coal blocks through the process of competitive bidding should be on the same basis as the Scheme of Ultra Mega Power Projects. The objective should be low cost power by way of competitive bids for coal as well as power projects. Obviously, consumers will benefit from less expensive power supply.

B&E: If the pending Bill on Coal reforms which will allow private players to mine coal for non-captive usage is passed, will it bring about much needed power shortages under control?
RVS:
While the power sector reform has moved forward, commencing from the historic legislation Electricity Act 2003, followed by several other policy initiatives, coal sector reform process has remained stagnant at the point when the Bill on coal was introduced in Parliament in 2001. Therefore, the present legislative initiative is a welcome move of the Ministry of Coal. The power industry is heavily dependent on coal just as coal industry has the largest consumers in the power sector, to the extent of 75% of its production. The present mismatches in reform initiatives are causing avoidable adverse impact not only on power sector but on economy as a whole. Therefore, coal sector reforms have to catch up fast with the actions that have happened, and will happen more rapidly, in the power sector.


Source : IIPM Editorial, 2012.